A kitchen renovation in Dubai typically costs AED 10,000-30,000 for a cosmetic refresh, about AED 20,000-70,000 to replace a 1-2 bedroom apartment kitchen in the same layout, and about AED 75,000-165,000 for a villa kitchen with an island and a moved sink, all before appliances. Cabinets are the biggest line: roughly AED 800-1,200 per linear metre for modular units and AED 1,500-4,500 for custom lacquer or solid wood. Add AED 15,000-30,000 for a mid-range built-in appliance set, at least 10% contingency and 5% VAT.
How much does a kitchen renovation cost in Dubai in 2026?
A kitchen renovation in Dubai costs anywhere from about AED 10,000 to well over AED 150,000 in 2026, and the scope decides where you land far more than the size of the room does. Three scopes cover almost every project: a cosmetic refresh, a same-layout replacement and a full remodel.
| Scope | What changes | Published Dubai ranges | Range used in this guide |
|---|---|---|---|
| Cosmetic refresh | New doors or vinyl wrap, handles, worktop, splashback and tap. Carcasses, layout and appliances stay. | Property Finder: AED 10,000-30,000. Octopus: AED 15,000-30,000. | AED 10,000-30,000 |
| Same-layout replacement, apartment | Old kitchen out; new cabinets, stone worktop, splashback, sockets and lighting. Sink, hob and dishwasher stay in place. | Octopus: AED 35,000-55,000 for JVC and JBR apartments. Property Finder: AED 20,000-40,000 compact, AED 40,000-80,000 mid-size. | About AED 20,000-70,000 before appliances |
| Full remodel or villa kitchen | Layout change, island, sink or hob moved, ducted extraction, premium surfaces. | Octopus: AED 80,000-150,000+ for a full gut, AED 90,000-130,000 in villa communities. Property Finder: AED 80,000-150,000+ for large kitchens. | About AED 75,000-165,000 before appliances |
Published ranges from Property Finder (October 2025) and Octopus (November 2025). The right-hand column is built up from the line items and the two worked examples further down this page.
The published numbers disagree for ordinary reasons. One guide counts appliances and another leaves them out; some include labour, VAT and NOC fees while others list them separately; and a "compact" kitchen in one guide is a "mid-size" kitchen in the next. Octopus sells home renovation and maintenance work and Property Finder sells property listings, and neither shows the project data behind its ranges. Treat any single figure, including the ones on this page, as a way to test a written quote rather than as a price.
Where the money goes
Cabinets are the largest single line in nearly every kitchen, followed by appliances and the worktop. Two Dubai guides split a typical budget like this:
| Component | First Unicorn (share of total) | Property Finder |
|---|---|---|
| Cabinetry | AED 15,000-80,000 (40-50%) | AED 15,000-60,000+ |
| Worktops | AED 5,000-40,000 (10-15%) | AED 3,000-15,000 |
| Appliances | AED 8,000-60,000 (15-20%) | AED 5,000-30,000 |
| Plumbing and fixtures | AED 3,000-15,000 (5-8%) | Not listed separately |
| Electrical and lighting | AED 2,000-8,000 (3-5%) | Lighting AED 1,000-5,000 |
| Tiling and splashback | AED 3,000-12,000 (5-8%) | Not listed separately |
| Flooring | AED 4,000-15,000 (5-8%) | AED 5,000-20,000 |
| Labour | Not listed separately | AED 5,000-15,000 |
First Unicorn gives AED ranges and shares of the total; Property Finder gives AED ranges only. Their totals differ, so the shares are the more useful comparison.
If cabinets come out far from 40-50% of your quote, ask why. Either the cabinet specification is unusually high or low, or another line is carrying costs that belong elsewhere.
How much do kitchen cabinets cost per linear metre in Dubai?
Modular kitchens are quoted at about AED 800-1,200 per linear metre in Dubai, custom lacquer or solid wood at about AED 1,500-4,500, and imported European systems from about AED 3,000. Ask what one linear metre includes, base units only or base and wall units together, because quotes are not consistent and the answer changes how two rates compare.
| Cabinet type | Typical 2026 rate | Source | What you get |
|---|---|---|---|
| Flat-pack (IKEA and similar) | Priced per unit, not per metre | IKEA UAE | AED 150 to measure the kitchen and AED 200 to plan it. IKEA fitters do no plumbing, gas or electrical work, so those trades are hired separately. |
| Modular: acrylic or sprayed MDF doors | AED 800-1,200 per linear metre | Octopus; First Unicorn | Standard carcass sizes with doors chosen from a finish range. Fillers close the gaps at walls and corners. |
| Custom lacquer or solid wood | AED 1,500-4,500 per linear metre | First Unicorn (solid wood AED 1,500-2,500); Octopus (AED 2,000-4,500); Arcan (extra cabinetry AED 2,000-5,000) | Built to the room, so dead corners and fillers disappear. Handleless profiles and ceiling-height doors sit in this band. |
| Imported European systems | AED 3,000+ per linear metre | First Unicorn | Made abroad to order and shipped. Get production and shipping dates in writing before booking the strip-out. |
Ranges as published; confirm whether fitting is included. VAT is usually extra. Tall units, appliance housings and end panels are often priced per piece rather than per metre.
Two things move a quote within its band. Internal fittings such as corner pull-outs, drawer inserts and larder mechanisms add 15-30% to the cabinet cost, according to Arcan. Hardware is the other: Arcan names Blum and Hettich for hinges, runners and drawer systems, and a quote that does not name the brand cannot be compared with one that does.
For a whole kitchen, Arcan's 2026 figures run from AED 8,000 for a compact melamine galley to AED 65,000 or more for an island kitchen in solid wood with stone tops, before 5% VAT. Property Finder puts pre-made cabinetry from AED 5,000 and custom cabinetry from AED 20,000 to past AED 60,000. Custom cabinets take about 20-35 working days to manufacture once the design is approved.
Door finish and carcass material decide how a kitchen copes with steam, spills and the occasional leak under the sink; that is a design question, covered in the kitchen design guide. For made-to-measure units, see the custom kitchen cabinets page.
What do quartz, granite, marble and porcelain worktops cost?
Standard granite is the cheapest stone worktop in Dubai and Italian marble or sintered stone the dearest: from roughly AED 190 per running metre for granite cut and fitted, to AED 720-1,500 per running metre for marble or Dekton supplied and installed. Engineered quartz sits between them, from about AED 450 per running metre.
| Material | Quoted rate | What the rate covers | Per running metre, 600 mm deep |
|---|---|---|---|
| Standard granite | AED 70-150 per sqm | Slab only (Marmara). Fabrication AED 120-250 per metre and fitting AED 40-90 per sqm on top. | About AED 190-390 |
| Imported granite (Brazilian, exotic) | AED 200-500 per sqm | Slab only (Marmara), same extras. | About AED 265-605 |
| Engineered quartz | From AED 750 per sqm | Supplied and installed (Octopus). Property Finder gives AED 200-700 per sqm for quartz or granite without saying what is included. | From about AED 450 |
| Italian marble (Carrara, Calacatta, Statuario) | AED 350-900+ per sqm slab; AED 1,200-2,500 per sqm installed | Slab only (Marmara); supplied and installed (Octopus). | About AED 350-840 from slab rates; AED 720-1,500 installed |
| Sintered stone or porcelain slab (Dekton, Neolith) | AED 1,200-2,500 per sqm | Supplied and installed, grouped with Italian marble (Octopus). | About AED 720-1,500 |
Per-metre figures are calculated: a 600 mm deep worktop covers 0.6 sqm per running metre. Slab-only rows add Marmara's fabrication rate (AED 120-250 per metre) and fitting rate (AED 40-90 per sqm for granite, AED 35-80 for marble). Marmara notes that cutting, transport and installation can add 20-40% beyond the material cost.
Most of the spread comes from what each number covers. Marmara's figures are a stone supplier's slab prices, with cutting, edging and fitting billed on top. Octopus's figures come from a Dubai renovation company's guide and read as prices for a finished, installed top. Arcan quotes AED 400-1,800 per linear metre for worktops across materials from laminate to sintered stone, which brackets both.
Each material behaves differently in a Dubai kitchen. Quartz is non-porous and needs no sealing, which makes it the low-maintenance choice for busy family kitchens and rentals. Granite takes hot pans better and costs less, but wants periodic sealing. Marble etches with lemon, vinegar and tomato and stains with turmeric, so it suits owners who accept a patina; the types of marble guide compares the stones. Sintered stone resists heat, scratches and sunlight, which is why it turns up on islands and outdoor kitchens. For marble tops supplied and fitted, see the marble countertops page.
Small details add fabrication time and money: each sink or hob cut-out, a mitred or thickened edge, a waterfall end on an island and a full-height splashback cut from the same slab. Ask for each one as its own line.
How much do appliances, plumbing, electrics and gas add?
Appliances add AED 15,000-30,000 for a mid-range built-in set and AED 40,000-100,000 for high-end brands, and moving the sink, hob or gas point adds AED 3,000-20,000 depending on what moves. These are the lines most often missing from a first quote.
Retail prices are a useful check on appliance budgets. On 13 November 2026 ACE UAE listed a Bosch Series 6 76 litre built-in oven at AED 3,059 on offer (AED 3,399 regular) and a Bosch 60 cm built-in induction hob, model PXX675DV1E, at AED 4,679 on offer (AED 5,199 regular). Those two come to about AED 7,700-8,600; an integrated dishwasher, hood, fridge-freezer and microwave make up the rest of a mid-range set.
| Item | Typical 2026 range | Source | When it applies |
|---|---|---|---|
| Mid-range built-in appliance set (Bosch, Siemens, AEG) | AED 15,000-30,000 | Octopus; First Unicorn gives AED 15,000-25,000 for Bosch or Siemens | Oven, hob, hood, dishwasher, fridge-freezer. Often left out of kitchen quotes. |
| High-end appliance set (Miele, Gaggenau, Wolf) | AED 40,000-100,000 | First Unicorn AED 40,000-80,000; Octopus AED 50,000-100,000 | Usually paired with fully integrated or concealed cabinetry. |
| Moving plumbing or electrical points | AED 5,000-20,000 | First Unicorn AED 5,000-15,000; Octopus AED 5,000-20,000 | Sink moved, island water point, new appliance circuits. |
| Moving a gas point | AED 3,000-8,000 | First Unicorn | Licensed gas contractor; Civil Defence approval for major modifications. |
| Distribution board upgrade | AED 3,000-8,000 | Octopus | When an induction hob and built-in oven exceed the existing board. |
| Electrician or plumber by the hour | AED 100-350 per hour | Bestimate AED 100-150; Octopus AED 150-350 for licensed trades | Small changes outside a fixed-price package. |
| Under-cabinet LED strip, fitting | AED 150-700+ | Bestimate | Per job; a separate switched circuit is worth asking for. |
| Ducted extraction upgrade | AED 2,000-5,000 | First Unicorn | Only where the building allows a duct route; otherwise a recirculating hood. |
| Strip-out and disposal | AED 800-5,000 | Octopus AED 800-2,500 for waste and licensed disposal; First Unicorn AED 3,000-5,000 with demolition | Low end: a small kitchen with the floor kept. |
| Porcelain floor, installed | AED 80-150 per sqm | First Unicorn; natural stone AED 200-400 per sqm | Plus AED 15-30 per sqm to lift old floor tiles (Tile Mountain UAE). |
| Splashback tiles, supply only | AED 70-200 per sqm | Tile Mountain UAE: ceramic wall tiles AED 70-120, glass or marble AED 120-200 | Fixing labour on top. |
| Re-waterproofing under tiles | AED 1,500-4,000 | Octopus | Only if a leak or failed membrane turns up behind the old units. |
| Island carcass and fitting | AED 10,000-20,000 | First Unicorn | Before the worktop and any plumbing to the island. |
Quoted ranges from Dubai renovation guides and suppliers, 2026. Confirm whether each line includes 5% VAT.
Gas needs its own planning. Many Dubai buildings run central gas from licensed suppliers such as Emirates Gas or SERGAS, and Civil Defence approval is required for new gas installations or major modifications. Property Finder puts the security deposit for a new connection at AED 2,000 for apartments and AED 4,000 for villas, plus an activation fee of up to AED 330. Switching to induction takes the gas line out of the quote, but check the electrical load first, because an induction hob and a built-in oven on an older board is a common reason for a board upgrade.
Floor and splashback tiling cover small areas in a kitchen, so they rarely decide the budget; the tiling cost guide has fixing rates per sqm by tile type. Keep a contingency of at least 10%. Octopus suggests 10-15%, because water damage behind old units only shows once they come out.
Worked example: what does a 1-2 bedroom apartment kitchen cost?
A same-layout renovation of an L-shaped kitchen in a 1-2 bedroom Dubai apartment comes to about AED 20,000-36,000 with modular cabinets, or about AED 39,000-70,000 with custom lacquer cabinets, quartz and a new floor, before appliances. Here is how those totals are built.
The kitchen: about 8 sqm of floor, 5 linear metres of base and wall cabinets including a tall oven housing, 4.5 m of 600 mm deep worktop and about 2.5 sqm of splashback. The sink, hob and dishwasher stay where they are, so there is no drainage work and usually no authority permit, only the building NOC.
| Line | Budget spec (AED) | Mid spec (AED) | Basis |
|---|---|---|---|
| Strip-out and disposal | 1,500-3,000 | 2,000-4,000 | Inside the published AED 800-5,000 spread; the mid version also lifts the floor tiles. |
| Cabinets, 5 linear metres | 4,000-6,000 | 10,000-15,000 | AED 800-1,200 per metre modular; AED 2,000-3,000 per metre custom lacquer. |
| Internal fittings (pull-outs, drawer inserts) | None | 1,500-4,500 | 15-30% of the cabinet line (Arcan). |
| Worktop, 4.5 m x 600 mm (2.7 sqm) | 1,100-3,000 | 2,000-3,250 | Budget: granite or entry quartz at AED 200-700 per sqm plus AED 120-250 per metre fabrication. Mid: quartz at AED 750-1,200 per sqm installed. |
| Splashback, about 2.5 sqm | 350-550 | 1,900-3,000 | Budget: ceramic tiles at AED 70-120 per sqm plus fixing. Mid: full-height quartz at AED 750-1,200 per sqm. |
| Floor, about 8 sqm | Existing floor kept | 650-1,200 | Porcelain at AED 80-150 per sqm installed. |
| Plumbing and fixtures | 3,000-5,000 | 4,000-7,000 | Reconnect sink and dishwasher, new sink and mixer; published band AED 3,000-15,000. |
| Electrical and lighting | 2,000-3,500 | 3,000-6,000 | Hob circuit check, extra sockets, under-cabinet LED; published band AED 2,000-8,000. |
| Fitting labour, protection, supervision | 5,000-8,000 | 8,000-15,000 | Property Finder: AED 5,000-15,000 for a mid-range kitchen. |
| Building NOC fee | 500-2,000 | 500-2,000 | Apartment NOC fee per First Unicorn; the refundable deposit is not counted. |
| Subtotal | 17,450-31,050 | 33,550-60,950 | Sum of the lines above. |
| Contingency, 10% | 1,745-3,105 | 3,355-6,095 | Octopus suggests 10-15%. |
| VAT, 5% | 960-1,710 | 1,845-3,350 | On works and contingency. |
| Total before appliances | About 20,000-36,000 | About 39,000-70,000 | Rounded. |
Worked from the quoted ranges on this page. Budget spec: modular doors, granite or entry quartz, ceramic splashback, existing floor and appliances kept. Mid spec: custom matt lacquer, Blum or Hettich hardware, quartz top and splashback, new porcelain floor.
Appliances go on top. A new Bosch or Siemens built-in set at AED 15,000-25,000 brings the budget version to about AED 35,000-61,000 and the mid version to about AED 54,000-95,000. If the sink moves to another wall or a new peninsula, add AED 5,000-15,000 for plumbing and electrics and allow for an authority permit. For the rest of the flat, the apartment renovation cost guide prices flooring, bathrooms and painting per sqm.
Worked example: what does a villa kitchen with an island cost?
A villa kitchen with a new island and the sink moved into it comes to about AED 75,000-165,000 before appliances, or about AED 90,000-195,000 with a mid-range built-in set.
The kitchen: about 18 sqm, a U-shaped run of 9 linear metres of custom lacquer or solid wood cabinets with a tall bank, a 2.4 m island holding the sink, a quartz perimeter top and a marble or sintered stone island top, a full-height quartz splashback, a new porcelain floor and ducted extraction.
| Line | AED | Basis |
|---|---|---|
| Strip-out and disposal | 3,000-5,000 | First Unicorn, demolition and disposal. |
| Perimeter cabinets, 9 linear metres with a tall bank | 18,000-40,500 | AED 2,000-4,500 per metre, custom lacquer or solid wood (Octopus). |
| Island carcass and fitting, 2.4 m | 10,000-20,000 | First Unicorn. |
| Internal fittings | 2,700-12,150 | 15-30% of the perimeter cabinet line (Arcan). |
| Worktops: 7 m quartz perimeter (4.2 sqm) and a 2.4 x 1.0 m island top (2.4 sqm) in marble or sintered stone | 6,030-11,040 | Quartz AED 750-1,200 per sqm; island AED 1,200-2,500 per sqm installed (Octopus). |
| Full-height quartz splashback, 4 sqm | 3,000-4,800 | AED 750-1,200 per sqm. |
| Porcelain floor, 18 sqm | 1,440-2,700 | AED 80-150 per sqm installed. |
| Sink moved to the island: water, drainage, power | 5,000-15,000 | First Unicorn. |
| Electrical and lighting: island sockets, pendants, LED | 3,000-8,000 | First Unicorn electrical band. |
| Ducted extraction | 2,000-5,000 | First Unicorn. |
| Fitting labour, protection, supervision | 10,000-15,000 | Property Finder AED 5,000-15,000; First Unicorn AED 10,000-15,000 with permits on high-end jobs. |
| Community NOC and authority fees | 1,000-3,500 | Octopus. Deposit and any consultant drawings not counted. |
| Subtotal | 65,170-142,690 | Sum of the lines above. |
| Contingency, 10% | 6,515-14,270 | Octopus suggests 10-15%. |
| VAT, 5% | 3,585-7,850 | On works and contingency. |
| Total before appliances | About 75,000-165,000 | Rounded. |
| With a mid-range set (AED 15,000-30,000) | About 90,000-195,000 | Bosch, Siemens or AEG. |
| With a high-end set (AED 50,000-100,000) | About 125,000-265,000 | Miele, Gaggenau or Wolf, per Octopus. |
Worked from the quoted ranges on this page. The refundable community deposit is not included.
Many Dubai villas have a second, closed kitchen for heavy cooking beside the show kitchen. Price it as a second, simpler kitchen with its own cabinets, top and extraction, not as an extra line on the first. Villa communities run their own NOC process, and moving the sink usually brings an authority permit as well. The villa renovation cost guide covers whole-villa budgets.
Adding an outdoor kitchen
A freestanding stainless steel outdoor kitchen is the cheapest route. Danube Home lists a 2.35 m three-module set (sink, appliance and grill modules plus a fridge) at AED 12,499 on offer, AED 18,999 regular, out of stock when checked, and a 4.25 m five-piece set at AED 21,999 on offer, AED 33,799 regular, both with installation included. A built-in masonry outdoor kitchen is a small building project instead: it needs an outdoor power supply, a water point and drain, a gas line unless the grill runs on bottled gas or charcoal, and community approval for external works. New gas installations need Civil Defence approval. For the worktop, sintered stone and granite cope best with sun and heat.
How long does a kitchen renovation take, and which approvals do you need?
On site, a cosmetic refresh takes about 1-2 weeks, a same-layout replacement 3-5 weeks and a full remodel 6-10 weeks, according to Octopus; the building NOC and cabinet manufacture come before that and usually overlap.
| Stage | Typical time | Notes |
|---|---|---|
| Selections locked | 3-4 weeks before work starts | Octopus advises finishing choices this early so stone, cabinets and appliances arrive on time. |
| Building or community NOC | Often 3-10 working days; 1-3 weeks with wet-area or layout changes | Comes first. No demolition until it is in writing. |
| Authority permit, if plumbing, drainage, gas or walls change | Often 1-4 weeks after the NOC | Dubai Municipality, Trakhees or DDA, depending on where the property is. |
| Custom cabinet manufacture | 20-35 working days from design approval | Runs in parallel with the approvals (Arcan). |
| On site: cosmetic refresh | 1-2 weeks | Octopus. |
| On site: same-layout replacement | 3-5 weeks | Octopus, mid-range remodel. |
| On site: full remodel | 6-10 weeks | Octopus, full gut renovation. |
Approval times are typical ranges reported by contractors and consultants, not official service levels.
Approvals come in two layers, set out in full in the renovation NOC and permit guide. A written NOC from the building management or master developer is needed for practically any kitchen refit, including a like-for-like replacement. An authority permit from Dubai Municipality, Trakhees or DDA, depending on the area, is typically added when drainage, water points, the wet-area layout or walls change. Gas changes bring in Civil Defence, and DEWA can be involved if the connected load changes. Tenants need the landlord's written consent before the building will accept an application.
Fees vary by building and authority. First Unicorn puts an apartment building NOC fee at AED 500-2,000 and Octopus puts Dubai Municipality NOC fees at AED 1,000-3,500, on top of a refundable deposit held against damage to lifts and corridors.
On site the order rarely changes: strip-out, plumbing and electrical first fix, floor and wall preparation, cabinets, then the worktop. Stone is templated only once the cabinets are fixed and level, then cut off site, so expect several working days without a worktop; set up a kettle and microwave in another room. The splashback, appliances and final connections follow, then snagging.
Where can you save without the kitchen looking cheap?
Keep the sink, hob and gas point where they are. That one decision removes the AED 5,000-20,000 of plumbing and electrical moves, most of the approval time and much of the risk of finding damage inside the walls.
- Reface sound carcasses. New doors or a vinyl wrap, handles, splashback and hardware is the cheapest visual upgrade in Octopus's guide, at AED 15,000-25,000. It only works when the base units are dry, square and not swollen.
- Spend on what you touch. Hinges, drawer runners and the worktop take daily wear; a door finish one grade down is less noticeable than a drawer that sags.
- Pick quartz or granite over marble. On a 2.7 sqm apartment top, quartz from AED 750 per sqm installed costs about AED 2,000, against AED 3,200-6,750 for Italian marble at AED 1,200-2,500.
- Buy appliances yourself. Retailers discount built-in appliances often; both Bosch items above were 10% off when checked. Give the contractor model numbers early so housings and cut-outs match.
- Use flat-pack in a rental. IKEA UAE charges AED 150 to measure and AED 200 to plan a kitchen, but its fitters do not do plumbing, gas or electrics, so budget a plumber and electrician separately.
How do you compare kitchen renovation quotes?
Put the quotes side by side on the same units and the same inclusions; most gaps between Dubai kitchen quotes come from what is left out, not from the price of the work. Check that each quote states:
- Cabinets: linear metres, what one metre includes, carcass material, door finish and hardware brand.
- Worktop: material, brand and colour, thickness, edge profile, cut-outs, upstand or full splashback, and templating after the cabinets are fitted.
- Appliances: listed by model, or written as excluded.
- MEP: every moved point listed, with the hob circuit and board capacity checked.
- Approvals: who applies for the NOC and any permit, and who pays the fees and the deposit.
- VAT: shown as its own 5% line.
- Variations: how hidden damage behind the old units is priced, with photos before extra work starts.
- Payment, warranty and dates: staged payments tied to milestones, warranty terms for cabinets, hardware and workmanship, and lead times in the contract.
The guide on how to choose a renovation company in Dubai covers licence and insurance checks. For a line-by-line kitchen quote, see Renovel's kitchen renovation service or send photos and a floor plan through the contact page.
Frequently Asked Questions
How much does a kitchen renovation cost in Dubai in 2026?
▾
Typical 2026 quotes run AED 10,000-30,000 for a cosmetic refresh that keeps the carcasses, about AED 20,000-70,000 to replace a 1-2 bedroom apartment kitchen in the same layout, and about AED 75,000-165,000 for a villa kitchen with an island and a moved sink. Those figures exclude appliances: add AED 15,000-30,000 for a mid-range built-in set or AED 40,000-100,000 for Miele, Gaggenau or Wolf.
How much does an apartment kitchen renovation cost in Dubai?
▾
For an L-shaped kitchen of about 8 sqm with 5 linear metres of cabinets, expect about AED 20,000-36,000 with modular cabinets, a granite or entry quartz top and the existing floor, or about AED 39,000-70,000 with custom lacquer cabinets, a quartz top and splashback and a new porcelain floor. Both include 10% contingency and 5% VAT but not appliances.
How much do kitchen cabinets cost per metre in Dubai?
▾
Modular kitchens with acrylic or sprayed MDF doors are quoted at about AED 800-1,200 per linear metre. Custom lacquer or solid wood runs about AED 1,500-4,500, and imported European systems start around AED 3,000. Pull-outs, corner units and drawer organisers add 15-30% to the cabinet price, and 5% VAT usually comes on top.
Which is cheaper for a Dubai kitchen worktop: granite, quartz or marble?
▾
Standard granite is the cheapest stone, with slabs from about AED 70-150 per sqm plus AED 120-250 per metre for cutting and edging. Engineered quartz is quoted from about AED 750 per sqm installed. Italian marble and sintered stone such as Dekton are quoted at AED 1,200-2,500 per sqm installed. On a 600 mm deep top, one sqm covers about 1.7 running metres.
Are appliances included in a kitchen renovation quote in Dubai?
▾
Often not. Many quotes price cabinets, worktops, MEP and finishes, then list appliances as a separate line or as supplied by the client. A mid-range built-in set from Bosch, Siemens or AEG costs about AED 15,000-30,000. Ask for model numbers so you can check the quote against retail prices.
Do I need a permit to renovate my kitchen in Dubai?
▾
You almost always need a written NOC from the building management or master developer, even for a like-for-like kitchen. An authority permit from Dubai Municipality, Trakhees or DDA is usually added when drainage, water points, gas or walls change, and new or heavily modified gas installations need Civil Defence approval. Tenants also need the landlord's written consent.
How long does a kitchen renovation take in Dubai?
▾
On site, a cosmetic refresh takes about 1-2 weeks, a same-layout replacement 3-5 weeks and a full remodel 6-10 weeks. Before that, allow for the building NOC (often 3-10 working days for simple work, 1-3 weeks with plumbing changes) and 20-35 working days to manufacture custom cabinets, which can run at the same time.
Is it cheaper to reface or replace kitchen cabinets in Dubai?
▾
Refacing is far cheaper when the carcasses are dry and square. New doors or a vinyl wrap with new handles, splashback and hardware is quoted at about AED 15,000-25,000, against roughly AED 20,000-70,000 to replace an apartment kitchen. Replace instead if the base units have swollen from leaks or the layout no longer works for you.